Littlefield’s Bryan Gregory gave an update from Teinert on the new high school, stating, Teinert is currently on schedule at the new high school building.
Structural steel is 90% complete, exterior framing and sheathing is 70% complete and mechanical/ electrical/plumbing rough-in on the first floor is 100% complete.
They are currently working on interior wall framing on the first floor and mechanical/electrical/ plumbing rough-in on the second floor.
The big upcoming milestones are completion of interior wall framing on the first floor by mid-March, completion of second floor interior wall framing by the end of April and completion of roofing by mid-May. The completion of those milestones will allow them to start interior finishes.
Teinert also gave an update on the Junior High, saying, the junior high Infill Addition is currently in the structure/foundation phase of construction.
They finished pouring concrete footings at the end of January and we have started underground electrical and plumbing rough-in. Once the underground rough-in is complete we will pour a slab on grade and start erecting structural steel.
The upcoming milestones for the Junior High Infill Addition is completion of the slab on grade by mid-March and completion of structural steel by mid-April.
The completion date for the high school is Christmas of 2024. Once the high school is completed the students and staff will move out of the existing building and into the new building which will allow the construction team to start remodeling what will ultimately be the new junior high.
The junior high is scheduled to start during Christmas break of 2024 and be completed by Christmas of 2025.